What a facility management contract in Jubail should include

Scope, service levels, pricing bases and the clauses that stop a camp or plant contract from turning into a monthly argument. Written for procurement and HSE managers signing their first facility services contract in the Eastern Province.

October 20268 minute readFacility management

Why Jubail contracts are different

Jubail Industrial City is run by the Royal Commission, its plants work on shutdown and turnaround cycles, and most of its workforce lives in camps outside the fence. A facility contract there has to cope with headcounts that double for a six-week turnaround, summer temperatures that decide when outdoor work happens, and client HSE rules that are stricter than the municipality’s. A contract written for an office tower in Riyadh will not survive it.

The ten clauses that matter

1. A scope matrix, not a scope paragraph

List every service, every area and every frequency in a table: rooms cleaned daily, washrooms three times a day, dining hall after every service, generators serviced monthly. Ambiguity in scope is where most disputes start, and a matrix is the only format both sides read the same way.

2. Service levels and how they are measured

A service level is a number, a method and a consequence. Response time to a breakdown call, cleaning inspection score, meal count accuracy, occupancy report on time. State who measures it, how often, and what happens when it is missed.

3. A pricing basis per service

Each service should be priced the way you budget for it. Accommodation and catering per person per day, manpower per hour from an approved timesheet, transport per vehicle per month, cleaning and maintenance as a monthly contract to the scope matrix. Mixed bases on one line make the invoice impossible to check.

Service
Usual pricing basis
What the rate should include
Worker accommodation
Per person per day
Bed, bedding, utilities, Wi-Fi, housekeeping of common areas, camp boss, security
Catering
Per person per day
Agreed meals, kitchen staff, hygiene records, water and disposables where ticked
Manpower (Ajeer)
Per hour or per month
Wages, sponsorship, Ajeer permit, accommodation, transport, supervision
Transport
Per vehicle per month
Driver, fuel, maintenance, insurance, GPS, standby
Housekeeping, maintenance, laundry
Monthly contract
Staff, supervisor, chemicals, consumables, common spares, reporting
Pest control, landscaping, security
Monthly contract
Scheduled visits or posts, call-outs, records and certificates

4. Mobilisation plan with dates

Who arrives when, with what equipment, and what counts as mobilised. For a camp that is beds made, kitchen live and gate manned on an agreed date; for a plant it is technicians inducted and spares on site. Attach the plan to the contract.

5. Supervision and the duty line

Name the supervisor, the hours they are on site and the number that answers at two in the morning. A contract without a named supervisor is a contract with nobody to call.

6. Compliance the client can inspect

Nitaqat band of the provider, Ajeer permits for every outsourced worker, ISO 9001, 14001, 45001 and 22000 systems where relevant, Civil Defence approvals for the camp, municipality licence, medical certificates for food handlers. List them and attach the certificates; a provider that cannot attach them should not be shortlisted.

7. Consumables, spares and who pays

State whether chemicals, bedding replacement, common spares and fuel are inside the rate or at cost, and the approval threshold above which the provider must quote before buying.

8. Call-outs and response times

Define the categories, for example a kitchen chiller or a generator as critical, a door handle as routine, and attach a response and a fix time to each. Agree what standby capacity exists for critical loads.

9. Variations and headcount changes

Headcount in Jubail moves with the project. Write the mechanism for adding or removing beds, meals and workers, the notice period, and how the per-person rate changes with volume bands, so a turnaround does not need a contract amendment.

10. Reporting, review and exit

Weekly occupancy and timesheets, monthly review with KPIs and open items, and a hand-over clause that returns rooms, assets and records in an agreed state. Exit is easier to write before the relationship than during it.

Red flags on a proposal

A single lump-sum monthly price with no scope matrix behind it.

No named supervisor and no duty line.

Sub-contracted cleaners or guards the provider does not sponsor.

Certificates promised rather than attached.

Pricing that cannot be reconciled to a headcount, a timesheet or a vehicle list.

How BICC writes it

BICC contracts in Jubail start from a scope matrix and a site walk, price each service on the basis above, name the supervisor and the duty line, and attach the Nitaqat, Ajeer, ISO and camp approvals. Occupancy, meal counts, timesheets and checklists are logged on a CAFM system and reviewed with the client every month, so the invoice and the log say the same thing.

Questions

Frequently asked about FM contracts.

Should accommodation, catering and cleaning be one contract or three?

One contract with one supervisor usually costs less and removes the gaps between providers, as long as each service keeps its own pricing basis and service levels inside the contract.

What contract length is normal in Jubail?

Twelve months or the project duration for camps and facility services; shutdown support is contracted for the turnaround window with a mobilisation and demobilisation plan.

How are turnaround peaks handled?

Through a variation clause with volume bands, so beds, meals and workers can be added for the shutdown weeks at pre-agreed rates and removed afterwards without renegotiation.

What should the monthly report contain?

Occupancy by block, meal counts against headcount, timesheets by trade, cleaning inspection scores, call-outs and response times, open items and the compliance records renewed that month.

Can BICC take over an existing contract mid-term?

Yes. A site walk, an asset and headcount baseline and a mobilisation plan allow a hand-over from an outgoing provider within about two weeks.

Related services

Related services and locations

Contact

Send us your scope and we will price it line by line.

A scope matrix and a quotation within 48 hours, with the certificates attached.