Establishments with fewer than 250 targeted workers must have their workers in licensed group housing when the final phase begins on 1 February 2027. The quickest route is to contract units that already hold a licence and prove the lease on Balady with a Collective Residence Certificate. This guide gives the steps, the checks and the order for moving crews without stopping work.
Establishments whose targeted workforce is below 250 workers must use licensed group housing before the final phase of the obligation begins on 1 February 2027.
The National Program for Developing Collective Housing for Individuals, chaired by the Ministry of Municipalities and Housing, announced this on 29 October 2026. The programme calls the time until the deadline a corrective period and urges establishments to complete licensing or contract licensed units within it.
Contracting units that are already licensed is normally the faster route, because the building inspection and the licence are already in place.
Licensing your own building means you must bring the building up to the health, technical and safety requirements, apply, pass inspection and wait for the result. Contracting means choosing a provider, checking the licence and proving the lease. The programme accepts both routes.
Factor | License your own building | Contract licensed units |
|---|---|---|
Building works | You carry out any works the requirements call for. | The licence holder has already done them. |
Inspection | Your building must pass municipal inspection. | Already completed for the licensed unit. |
Who runs the building | You, with the supervisor the rules require. | The licence holder or operator. |
Proof on Balady | Your own licence. | A Collective Residence Certificate for your lease. |
Best when | You own a suitable building and want to run it. | You need beds soon or do not want to run housing. |
Group housing licence in Saudi Arabia: your own licence or a licensed provider
Start with a count and a decision, because both set how long the rest takes.
The tenant establishment applies for a Collective Residence Certificate, which Balady describes as proof that eligible housing is available to the establishment’s workers.
Balady lists three conditions: a valid Collective Residence Licence, a valid rental relationship between the licence holder and the leasing establishment, and approval of the application by the licence holder. The establishment signs in through Absher, selects the applicant capacity, starts the issuance service and enters the licence number, the lease number and the rental dates. It then enters the bedrooms, bathrooms and total area, and the platform calculates the capacity automatically.
The request goes to the licence holder for approval. Balady lists the service as free, with a service duration of 10 days, and the page shows a service release date of 13 January 2026.
Check the paper and the building, because a licence number alone does not tell you whether the unit suits your crew.
Labour camp requirements in Saudi Arabia: the 2026 checklist
Move by crew and by shift, not by headcount alone, so that each site keeps a working team on every shift.
Ask the provider to approve your Balady certificate request on the day you sign the lease. The service is not instant, and an approval that waits with the licence holder can leave a gap between moving in and holding proof.
The sources published so far say that non-compliance may lead to regulatory procedures under the approved systems and guides, and they list no specific fine.
BICC therefore does not quote a penalty. The programme has called the period until 1 February 2027 a corrective period, so the practical advice is to complete licensing or contracting inside it and to keep the licence, lease and certificate on file. Check the Ministry of Municipalities and Housing and Balady for updates.
Group housing deadline of 1 February 2027: who is covered and what to do now
BICC runs its own camps in Jubail, Jeddah and Yanbu, and offers furnished staff housing in Al Khobar. In Riyadh, Dammam and at project sites, BICC sources, licenses and operates housing for the contract term, with meals, cleaning, laundry and transport added to the same agreement.
Send the headcount, the city and the start date, and BICC prepares a plan and quotation within 48 hours.
BICC worker accommodation in Saudi Arabia
BICC worker accommodation in Jeddah
WhatsApp +966 59 255 3333 or email info@bicc.com.sa with your headcount, city and start date.
No. The National Program for Developing Collective Housing for Individuals recognises two routes: license your own building, or contract units that are already licensed. The second route means you do not have to own or run a housing facility.
The programme statement of 29 October 2026 covers establishments whose targeted workforce is below 250 workers. Confirm your own category in your Qiwa and Balady accounts.
A tenant establishment applies for a Collective Residence Certificate on Balady. It enters the licence number, the lease number and dates, and the rooms, and the licence holder approves the request. Balady lists the service as free, with a service duration of 10 days.
The sources published so far say only that non-compliance may lead to regulatory procedures under the approved systems and guides. They list no specific fine, so BICC does not quote one.
You can, but moving by crew and shift usually keeps work running. Move a first group after the unit passes your checks, confirm the register and the certificate, and then move the next group.
Ask for the licence number and licensed capacity of the exact building, a written commitment to approve your Balady certificate, the room plan, the services included and the notice terms. Check that the capacity covers every worker you plan to house.
Tell us the headcount, city and start date, and we will send a plan and quotation within 48 hours.